The contractor continues to progress right along with UST project work. This week the contractor finished the underground stormwater retention system and completed backfilling up to the subgrade. The contractor is continuing to install underground utilities next week and beginning to deliver and install the base material under the concrete parking area and will install the trench drains. The contractor’s electrician will start work the week of June 26th in the lube room to install conduit and conductors.